Project Description
Design and construct a sidewalk on Clevland Ave. from Duncan Rd. (SR17) to Riverside Dr.Project Location
Clevland Ave. from Duncan Rd. (SR17) to Riverside Dr.Latest Updates
A purchase order was issued to start the design process. The engineer is scheduling the survay and setting up an pre-app meeting with SWFWMDBudget
Phase | Cost |
---|---|
Design | $77,100.00 |
Construction | $398,350.00 |
Total Budget | $475,450.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 04/24/2024 | 02/28/2025 | |
Construction | 03/03/2025 | 09/01/2025 | |
Turnover & Closeout | 10/01/2025 | 10/31/2025 |
Project Phase
Design Development
Last Updated
05/07/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
TBD
Construction Contractor
TBD