Project Description
This project will replace of approximately 1,980 linear feet of 6-inch wastewater force main.Project Location
Easy Street from U.S. 41 to Orange StreetLatest Updates
The installation of the new sewer force main is complete and in service.Budget
Phase | Cost |
---|---|
Construction | $383,165.48 |
Total Budget | $383,165.48 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 05/26/2021 | 11/30/2021 | 11/30/2021 |
Turnover & Closeout | 11/10/2021 | 01/03/2022 | 01/03/2022 |
Project Phase
Project Complete
Last Updated
01/03/2022
Project Manager
Jody Pressley
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Construction Contractor