Project Description
These 3 bridges require design services to implement the FDOT maintenance and repair items for each of the respective bridges.
Bridge #014030 Pellam Boulevard over Auburn Waterway
Bridge #014043 Wintergarden Avenue over Como Waterway
Bridge #014069 O'Hara Drive over Atlantus Waterway
Project Location
Bridge #014030 Pellam Boulevard over Auburn Waterway
Bridge #014043 Wintergarden Avenue over Como Waterway
Bridge #014069 O'Hara Drive over Atlantus Waterway
Latest Updates
BRIDGE #014069 O'HARA DRIVE OVER THE ATLANTUS WATERWAY IS CLOSED FOR AN EMERGENCY REPAIR. Construction bids are due May 1, 2024. Once the contract is approved and a notice to proceed has been issued we anticipate construction duration to be 45 to 60 days.
Project Activities for May 2024
The County has selected Kimley-Horn and Associates as the design firm, we expect the Bridge Repair Memorandum on May 15, 2024.
Budget
Phase | Cost |
---|---|
Design | $189,895 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 01/16/2024 | 10/01/2024 |
Project Phase
Design Development
Last Updated
05/01/2024
Project Manager
Kelly Slaughter
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Kimley-Horn Engineers