Project Description
This project is to design and construct a multi-use pathway on the West side of Kings Highway from Veterans Boulevard to Sandhill Boulevard.Project Location
Kings Highway from Veterans Boulevard to Sandhill Boulevard.Latest Updates
The contractor has completed his work and closeout of the project is being done.Budget
Phase | Cost |
---|---|
Design | $123,458.00 |
Construction | $497,435.00 |
Total Budget | $620,893.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 11/20/2020 | 03/31/2022 | |
Construction | 09/25/2023 | 03/29/2024 |
Project Phase
Construction
Last Updated
04/29/2024
Project Manager
Raymond Slade
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
American Consulting Professionals
Construction Contractor
TBD