2019 Paving Program

Latest Updates

The FY19 Paving Program has completed the paving process in all Districts of the origional contract and the Restoration is ongoing They have started paving operations in the Road and Bridge Change Order areas.

To date they have placed approx. 81,472 Tons of asphalt on the FY19 Paving Program.

The percentage of contract time that has elapsed is 62.08 percent and the percentage of work that has been completed is 63.19 percent

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 05/01/2018 09/01/2018
Design Development 05/01/2018 09/01/2018
Construction 03/04/2019 12/20/2019

Supporting Materials

Project Phase
Construction

Project Updated
04/07/2020

Project Manager
James Layport

Sponsor Department
Public Works

Construction Contractor
Ajax Paving, Inc