Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Burnt Store Road Phase II

Project Description

This project includes design, permitting, utility coordination, and construction to widen the remaining middle section of Burnt Store Road (4.4 miles) to a four-lane roadway from a point near Notre Dame Boulevard to a point north of Zemel Road. The design includes an open swale concept with a large median that will accommodate two future lanes. Stormwater ponds, concrete pipes, and structures will be installed to collect wastewater. Water, sewer, and reclaimed water mains are included in the project. Six foot wide sidewalks will be constructed along the east side and the southwest side of the roadway. LED street lights are also included. FDOT has contributed $4 million to the construction project through a grant. The remaining funding has been provided through the gas tax.

Project Location

Burnt Store Road from a point near Notre Dame Boulevard to a point north of Zemel Road.

Latest Updates

The project has been completed. 

Budget

Phase Cost
Design $3,331,723.18
Construction $26,392,594.27
Funding source(s): FDOT has contributed $4 million to the construction project through a grant. The remaining funding has been provided through the gas tax.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 07/13/2015 03/29/2019 03/29/2019
Design Development 07/13/2015 03/29/2019 03/29/2019
Construction 11/04/2019 12/17/2021 04/25/2022
Turnover & Closeout 12/15/2021 04/25/2022 04/25/2022

Supporting Materials

Burnt Store Road Phase II Project Image

Project Phase
Project Complete

Last Updated
06/21/2022

Project Manager
Lindsey Johnson

Public Relations
Tracy Doherty
Email Public Relations

Sponsor Department
Public Works

Design Engineer/Architect
Johnson Engineering

Construction Contractor
Wright Construction Group

Delivering Exceptional Service

Questions? Issues?

Contact Us