Ackerman Wastewater Expansion Project

Project Description

The Ackerman MSBU was approved in November 2019. This project includes construction of a wastewater collection system to service approximately 1,300 properties with sewer service, new water service lines and a vacuum station that will provide sewer collection for the wastewater system. 

Project Updates
  • Update 11/10/20: The BCC approved the contract for the Vacuum Station and Zones 1 and 2. Contractor: Guymann Construction of Florida, Inc. Construction is expected to commence: Spring 2021
  • Update 1/3/20: Unity of Title and Deferral forms due by Jan. 3, 2020.

Capital Projects Office
Phone: 941.764.4305
Email: S2S@CharlotteCountyFL.gov

Latest Updates

Guymann Construction was awarded the contract for the vacuum station and zones 1 and 2. Construction has started. 

Ackerman Avenue from Concert Street to Midway Boulevard will be closed starting Thursday, April 1.

Crews are currently working on the water main replacement at Hottelet Circle and Ackerman Avenue.

Budget

Phase Cost
Total Budget $26,948,870.00
Funding source(s):

Resident Assessments, Florida Department of Environmental Protection State Revolving Funds, EPA Grants, RESTORE, Utility Repair and Replacement Funds

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 11/19/2019 12/01/2020
Design Development 01/21/2021
Construction 04/05/2021

Supporting Materials

Project Phase
Construction

Last Updated
05/14/2021

Project Manager
Mike Martindell

Public Relations
Caroline Wannall
Email Public Relations

Sponsor Department
Utilities

Design Engineer/Architect
Giffels-Webster Engineers

Construction Contractor
Guymann Construction of Florida, Inc.