Project Description
The Ackerman MSBU was approved in November 2019. This project includes construction of a wastewater collection system to service approximately 1,300 properties with sewer service, new water service lines and a vacuum station that will provide sewer collection for the wastewater system.
Latest Updates
Guymann Construction was awarded the contract for the vacuum station and zones 1 and 2 starting. Construction is expected to commence Spring 2021.
Budget
Phase | Cost |
---|---|
Total Budget | $26,948,870.00 |
Resident Assessments, Florida Department of Environmental Protection State Revolving Funds, EPA Grants, RESTORE, Utility Repair and Replacement Funds
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 11/19/2019 | 12/01/2020 | |
Design Development | 01/21/2021 | ||
Construction | 03/22/2021 |
Supporting Materials
Project Phase
Construction
Last Updated
12/31/2020
Project Manager
Mike Martindell
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Design Engineer/Architect
Giffels-Webster Engineers
Construction Contractor
Guymann Construction of Florida, Inc.