Ainger Creek Bridge Repairs

Project Description

The Ainger Creek Bridge required various bridge repairs, the County selected a design firm to perform a detailed bridge inspection, prepare a repair memorandum and provide complete construction plans for the bridge repairs.

The project includes concrete repairs, expansion joint repairs, clean and seal bridge deck and approach slabs, approach guard rail replacement, replace sidewalk approach slabs, new concrete gravity wall (safety repair), replace portions of sidewalks, new aluminum pipe railing, replace existing rip rap at end bents, cleaning bridge and class V coating, replace pavement markings.

Project Location

The Aigner Creek Bridge locate on CR 775 (Placida Road) over Ainger Creek in Englewood.

Latest Updates

Completed Work as of October 19 - 30, 2020

Construction has started on the Ainger Creek Bridge Repair project.  The week of October 19, 2020 the Contractor is installing the maintenance of traffic and mobilizing equipment to the project site. The Contractor starting clearing and grubbing on the Northwest side of the bridge and demolition of the rip rap at the end bent on the North side under the bridge.

On October 20, 2020, the County is meeting with Englewood Water District staff to discuss the sewer line on the east side and water line on the west side of the bridge, we want to coordinate construction activities.

The week of October 26, 2020 the crews started the replacement of the Northeast side bridge approach slab, crews removed the old slab and new concrete poured.  On the Southeast side the crews prepped sidewalk approach slab removal and concrete pour.  Crews continue to also work under the bridge preparing for the Fabriform installation on the South side under the bridge.  

Upcoming Work Week of November 2, 2020

Budget

Phase Cost
Design $81,500.00
Construction $361,856.46
Other Costs $3,590.00
Total Budget $446,946.46

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 09/01/2019 04/01/2020
Design Development 05/01/2020 06/18/2020
Construction 10/19/2020 12/18/2020

Project Phase
Construction

Project Updated
10/30/2020

Project Manager
Kelly Slaughter

Project Number
2021000203

Design Engineer/Architect
Bridging Solutions

Construction Contractor
V & H Construction