Project Description
The Ainger Creek Bridge required various bridge repairs, the County selected a design firm to perform a detailed bridge inspection, prepare a repair memorandum and provide complete construction plans for the bridge repairs.
The project includes concrete repairs, expansion joint repairs, clean and seal bridge deck and approach slabs, approach guard rail replacement, replace sidewalk approach slabs, new concrete gravity wall (safety repair), replace portions of sidewalks, new aluminum pipe railing, replace existing rip rap at end bents, cleaning bridge and class V coating, replace pavement markings.
Project Location
The Aigner Creek Bridge locate on CR 775 (Placida Road) over Ainger Creek in Englewood.Latest Updates
The Project is complete. Please see the before and after pictures in the final slideshow.
Budget
Phase | Cost |
---|---|
Design | $81,500.00 |
Construction | $361,856.46 |
Other Costs | $3,590.00 |
Total Budget | $446,946.46 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 09/01/2019 | 04/01/2020 | |
Design Development | 05/01/2020 | 06/18/2020 | |
Construction | 10/19/2020 | 12/18/2020 | 12/10/2020 |
Turnover & Closeout | 12/10/2020 | 01/29/2021 |
Supporting Materials
Project Phase
Turnover & Closeout
Last Updated
12/20/2020
Project Manager
Kelly Slaughter
Public Relations
Brian Gleason
Email Public Relations
Project Number
2021000203
Sponsor Department
Public Works
Design Engineer/Architect
Bridging Solutions
Construction Contractor
V & H Construction