Project Description
Creation of a master plan through the park design process and phase 1 development. The project tasks consist of the following:
- Site Inventory and Analysis
- Data Gathering and Analysis
- Public Input Process
- Programming
- ADA Compliance review and recommendations
- Crime Prevention Through Environmental Design (CPTED) recommendations
- Conceptual Master Planning Alternatives
- Preliminary Master Plan
- Phasing Determination
Bissett Park is identified in the Local Mitigation Plan as a future location for a recreation center capable of providing emergency sheltering.
Project Location
Bissett Park
12455 Path Ave.
Punta Gorda, FL 33955
Latest Updates
First public meeting was held on May 25, 2021 to present a preliminary design concept to the public. The public present at the meeting gave feed back and the project team is working on make some adjustments to the concept plan. The adjusted plan will be presented at future public meeting.
The second public meeting was held on October 13, 2021. A revised plan based on comments from the first public meeting was proposed.
The final concept plan was presented at the Parks and Recreation Advisory board on 12/03/02021. Approval of the concept plan was granted and staff will start the design stage of Phase 1.
In the final design phase of the process.
The engineering firm has started the process for pre-DRC approval.
Bid documents have been completed and documents are being prepared for the bid process.
Budget
Phase | Cost |
---|---|
Design | $97,730.00 |
Construction | $500,000.00 |
Total Budget | $597,730.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 04/13/2020 | 04/13/2022 |
Supporting Materials
Project Phase
Design Development
Last Updated
05/03/2023
Project Manager
Lacey Solomon
Public Relations
Lacey Solomon
Email Public Relations
Project Number
c722101
Sponsor Department
Community Services
Design Engineer/Architect
Weiler Engineering Corporation