Project Description
Chamberlain over the Markham Waterway Bridge Rehabilitation will include necessary bridge repairs as noted in the Florida Department of Transportation Bridge Inspection Report, update bridge to current design codes, bat exclusion, and Charlotte County utility relocation.Project Location
This bridge rehabilitation project is located on Chamberlain Boulevard over the Markham Waterway, between McDill Drive and Ramblewood Street in Northwest Port Charlotte.Latest Updates
Upcoming Construction Activities Weeks for June 23 - July 7
The Contractor has completed the utility replacement of the watermain, valves, and tiebacks and is currently pending FDEP approval.
The Bridge is now open as of May 31, 2022.
The project is on schedule to be complete on June 27, 2022.
Our next progress meeting with the contractor is scheduled for June 24, 2022.
Budget
Phase | Cost |
---|---|
Design | $139,267 |
Construction | $949,316.64 |
Other Costs | $9,115.00 |
Total Budget | $1,097,698.64 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 02/19/2020 | 08/20/2021 | 08/03/2021 |
Construction | 03/14/2022 | 06/27/2022 |
Project Phase
Construction
Last Updated
06/23/2022
Project Manager
Kelly Slaughter
Public Relations
Tracy Doherty
Email Public Relations
Project Number
2020001548
Sponsor Department
Public Works
Design Engineer/Architect
American Consulting/CES
Construction Contractor
Zep Construction, Inc.