Project Description
This project includes the design and construction of new pedestrian sidewalks and drainage improvments on Melbourne Street from US 41 to Harborview Road.Project Location
Melbourne Street from US 41 to Harborview Road in Charlotte Harbor.Project Impacts
Due to Hurricane Ian, the scheduled has been delayed.Latest Updates
Johnson Engineering has started the initial survey and will move towards the 30 percent design phase. 30% plans are due on May 15, 2023
Budget
Phase | Cost |
---|---|
Design | $182,080 |
Construction | $686,000 |
Total Budget | $868,080 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 01/10/2022 | 07/11/2022 | 07/08/2022 |
Design Development | 07/12/2022 | 01/15/2024 | |
Construction | 05/13/2024 | 10/16/2024 | |
Turnover & Closeout | 10/16/2024 | 11/29/2024 |

Project Phase
Design Development
Last Updated
01/23/2023
Project Manager
Jeff Keyser
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c192205
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD