Project Description
This project provides for the construction of a stormwater control structure under Peachland Blvd at the Elkcam Waterway. As a result of the Stormwater Master Plan that was completed in 1998, it was determined that many of the existing stormwater control structures were either undersized or had deteriorated since the 1960’s when they were originally built. The new structure will replace (2) 48" RCP's and weir with (1) 10’x10’ box culvert and a weir.Project Location
Peachland Boulevard between Strasburg Drive and Alton TerraceLatest Updates
Construction started Monday, October 12, 2020.
The project is complete.
Budget
Phase | Cost |
---|---|
Design | $99710 |
Construction | $1,896,462.54 |
Total Budget | $1,996,172.54 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 08/11/2018 | 08/11/2019 | |
Construction | 10/12/2020 | 10/20/2021 | 10/08/2021 |
Turnover & Closeout | 10/12/2021 | 11/12/2021 | 11/12/2021 |
Project Phase
Project Complete
Last Updated
05/19/2022
Project Manager
Karen Bliss
Public Relations
Tracy Doherty
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering, Inc.
Construction Contractor
Thomas Marine