Project Description
The Englewood East Street and Drainage MSBU requested to design and construct sidewalks on Spinnaker Blvd. and Sunnybrook Blvd.Project Location
Spinnaker Blvd. East side of road -North Access Rd. to Willmington Blvd.
Sunnybrook Blvd.West side of road -North Access Rd. to Willmington Blvd.
Latest Updates
The project is complete finishing up closeout of the project.Budget
Phase | Cost |
---|---|
Design | $119,980.00 |
Construction | $799,575.00 |
Total Budget | $910,555.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 05/29/2019 | 02/23/2020 | 08/30/2020 |
Construction | 04/20/2020 | 11/16/2020 | 11/13/2020 |
Turnover & Closeout | 11/16/2020 | 11/30/2020 | 02/23/2021 |
Project Phase
Turnover & Closeout
Last Updated
02/23/2021
Project Manager
Raymond Slade
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Giffells-Webster Engineering
Construction Contractor
Pavement Maintenance Inc.