Gasparilla Road Intersections Signalization

Project Description

This project is designing and permitting and then constructing two signalized intersections out of the non-signalized intersection along Gasparilla Road.

Design four-way mast arm signalized intersection at Ingram/Ingraham Boulevard at Gasparilla Rd.

Design three-way mast arm signalized intersection at Rotonda East Boulevard at Gasparilla Road.

Project Location

 South Gulf Cove area.

The roadway intersection of Gasparilla Road and Ingram /Ingraham Blvd.  

The roadway intersection of Gasparilla Road and Rotonda East Blvd. 

Project Impacts

Improved safety features and hardening against future storms. 

Latest Updates

Kimley-Horn is the county’s design engineer for this project.

  • Initial surveys, Geotech, subsurface engineering, and coordination with utilities have all been completed
  • 60% plan submittal for both intersections have been received.
  • Rotonda E. intersection design is on hold at 60% design while county staff is working to provide round-about costs to the county board after receiving the request.
  • Ingram / Ingraham intersection signal design is currently at 100% design submittal and county staff has begun the review and comment phase.
  • Kimley-Horm has applied to SWFWMD for an exemption of permit for construction.
  • Ongoing utility coordination to design mast arm locations in a busy right of way.
  • Charlotte County Utility Department is working on locating their utilities and providing that info to the EOR as well as planning relocation of utilities in conflict with Mast Arm drill shaft locations. 

    Kimley-Horn is the county’s design engineer for this project.

  • Initial surveys, Geotech, subsurface engineering, and coordination with utilities have all been completed
  • 60% plan submittal for both intersections have been received.
  • Rotonda E. intersection design was on hold at 60% design while county staff was working to provide round-about costs to the county board after receiving the request. As of Feb., management made the decision to move forward with a signal in lieu of a round-about. The consultant has been notified to move forward and advance the design to 90%
  • Ingram / Ingraham intersection signal design is currently at 100% design submittal and county staff has begun the review and comment phase.
  • Kimley-Horm has applied to SWFWMD for an exemption of permit for construction.
  • Ongoing utility coordination to design mast arm locations in a busy right of way.
  • Charlotte County Utility Department is working on locating their utilities and providing that info to the EOR as well as planning relocation of utilities in conflict with Mast Arm drill shaft locations. 

Budget

Phase Cost
Design $299,901.00
Construction $2,000,000.00
Total Budget $2,299,901.00
Funding source(s): Various Interstions CIP fund

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 04/09/2024 12/13/2024 12/13/2024
Design Development 12/16/2024 12/16/2025
Construction 04/01/2026

Project Phase
Design Development

Last Updated
02/04/2026

Project Manager
Zach Patchell

Public Relations
Chad Ray
Email Public Relations

Project Number
TBD

Sponsor Department
Public Work Engineering

Design Engineer/Architect
Kimley-Horn

Construction Contractor
TBD