Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Hayward Canal Dredge

Project Description

This Engineering project consists of surveying, permitting, and design of a maintenance dredge project for the Hayward Waterway canal system, which includes the main channel and the interior canals. This project has been initiated by request of the citizens of the Hayward Waterway MSBU. Funding for the dredging of the access channel and main canal is through WCIND grant funding. The finger channels have been removed from this scope due to MSBU funding constraints and are being planned for a future project. The purpose is to restore depth and width, providing safe navigation to and from the public boat ramp. This canal / channel system has a history of maintenance dredging of which last occurred in 2017. Dredging is projected to go out to bid late summer of 2021. 

Project Location

Hayward Waterway System, El Jobean, Hayward canal.

Project Impacts

This project will result in improved access between the El. Jobean boat ramp and the Myakka River.

Latest Updates

This dredging project was awarded by the county to Sea and Shoreline Inc and the PO has been issued. The contractor and the county held a pre-construction meeting and agreed to a notice to proceed date of 6-6-22. At that time SSI will begin to mobilize on to the project. An upland spoil site will be set up on the county owned ROW at the end of Armada Rd adjoining the Schofield water way or at an alternate lot along the waterway that the contractor secures through a private agreement. Once site is complete the contractor will begin dredging. Usually within days of mobilizing in. Sea &Shoreline recently experienced a delay and will now be mobilizing in on 7-5-22. County staff has reminded the contractor of contract time and requirements.

Budget

Phase Cost
Design $39,700.00
Construction $182,248.50
Total Budget $221,948.50
Funding source(s): Hayward Waterway MSBU, WCIND grant funding

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 01/15/2019 12/01/2021
Construction 05/23/2022 09/01/2022
Turnover & Closeout 09/02/2022 09/05/2022
Hayward Canal Dredge Project Image

Project Phase
Construction

Last Updated
06/23/2022

Project Manager
Zach Patchell

Public Relations
Karlene McDonald
Email Public Relations

Project Number
s391905

Sponsor Department
Public Works

Design Engineer/Architect
Johnson

Construction Contractor
TBD

Delivering Exceptional Service

Questions? Issues?

Contact Us