Peachland Boulevard Sidewalk (HB41)

Project Description

Design and construct a 5' sidewalk on the north side of Peachland Boulevard from Atwater Street to Veterans Boulevard. as part of the safe routes to school (HB41) CIP

Project Location

Northside of Peachland Boulevard, Atwater Street to Veterans Boulevard.

Latest Updates

The contractor was given final acceptance on May 1st. and the close out of the final quantities is being done.

Budget

Phase Cost
Design $149,353.00
Construction $2,100,000.00
Total Budget $2,249,353.00
Funding source(s): The HB41 sidewalks are funded by gas tax.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 10/01/2018 01/31/2020 03/31/2020
Construction 03/08/2021 02/21/2022 04/01/2022
Turnover & Closeout 01/03/2022 02/01/2022

Project Phase
Turnover & Closeout

Last Updated
09/19/2022

Project Manager
Raymond Slade

Public Relations
Tracy Doherty
Email Public Relations

Sponsor Department
Public Works

Design Engineer/Architect
Johnson Engineering

Construction Contractor
Cougar Contracting