South Gulf Cove Pathways

Project Description

The South Gulf Cove Street and Drainage MSBU requested to design and construct a 10' multi-use pathway on San Domingo Boulevard.

Project Location

Phase 1- Ingraham Blvd. CR771 to Calumet Blvd. / Calumet Blvd. Ingraham Blvd. to St Paul Dr. = Complete

Phase 2- Ingraham Blvd. Calumet Blvd. to St. Paul Dr. / St. Paul Dr. Ingraham Blvd. to Appleton Blvd. = Complete

Phase 3- Appleton Blvd. CR771 to St. Paul Dr. / Keystone Blvd. CR771 to Hallendale Blvd. / San Domingo Blvd. CR771 to Calumet Blvd. / Calumet Blvd. Appleton Blvd. to Ingraham Blvd. / St Paul Dr. Ingraham Blvd. to Viscount Cir. = Complete

Phase 4- The East side of San Domingo Blvd. Calumet Blvd. to Calumet Blvd.

Latest Updates

The 90% plans were recieved 9/4/21 and are under review by staff.

Budget

Phase Cost
Design $85,722.00
Construction $750,000.00
Total Budget $835,722.00
Funding source(s): This project is funded by the South Gulf Cove Street & Drainage MSBU.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 03/01/2021 09/30/2021
Construction 03/01/2022 08/01/2022
Turnover & Closeout 09/01/2022 09/30/2022

Project Phase
Design Development

Last Updated
09/09/2021

Project Manager
Raymond Slade

Public Relations
Brian Gleason
Email Public Relations

Sponsor Department
Public Works

Design Engineer/Architect
Johnson Engineering

Construction Contractor
TBD