Project Description
This project includes the design and construction of seven (7) new turn lanes at various intersections within the county. The improvements consist of new right-turn lanes along with associated sidewalk modifications, drainage improvements, street light adjustments, and traffic signal hardening on Education Way, removing the old span wire system to new signal mast arms.Project Location
- Gasparilla Road at Keystone Boulevard
- Gasparilla Road at San Domingo Boulevard
- Paulson Drive/Murdock Circle at Veterans Boulevard
- Enterprise Drive at El Jobean Road (SR 776)
- Elkcam Boulevard at Midway Boulevard
- Education Way at Murdock Circle
- Education Way at Cochran Boulevard
Latest Updates
Charlotte County Board of County Commissioners has approved the rankings. Staff will start negotiations with Florida Transportation Engineering.
Budget
| Phase | Cost |
|---|---|
| Design | $1,000,000 |
| Construction | $6,000,000 |
| Total Budget | $7,000,000.00 |
Road Impact Fees
State Appropriation Funds
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 01/05/2026 | 05/18/2026 | 05/19/2026 |
| Design Development | 07/06/2026 | 11/01/2027 |
Supporting Materials
Project Phase
Design Development
Last Updated
06/01/2026
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
26-226
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
TBD