Rio Villa Bridge Rehabilitation

Project Description

The Rio Villa Bridge over the Venice Canal, originally constructed in 1973, is scheduled for repairs to extend its lifespan and ensure continued safe use.  This project includes procuring an engineering firm to design the necessary repairs, followed by contracting with a construction firm to carry out the rehabilitation work.

Project Location

The Rio Villa Bridge is situated on Rio Villa Drive between Wisteria Place and Magnolia Way and serves as the only bridge on this roadway.

Latest Updates

Project Update - August 2026

The design consultant is currently performing the bridge deck testing and load rating calculations -

  • Tierra's GPR deck scan and coring operation
  • They completed 6 concrete cores (with no rebar) for concrete strength testing and 2 cores (with rebar) for steel grade testing
  • They are analyzing the GPR scan data and developing their deck condition report
  • They are starting their in-house compression breaks and shipping the extracted steel to an outside lab for testing

Budget

Phase Cost
Design $95,000
Funding source(s): Road and Bridge

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 10/07/2025 11/26/2025
Design Development 03/30/2026 08/28/2026
Rio Villa Bridge Rehabilitation  Project Image

Project Phase
Design Development

Last Updated
08/04/2026

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Weiler Engineering Corp