Project Description
Remove hurricane debris from approximately 37 miles of navigable waterways througout the county. Please see attached map that shows which waterways are included in the project.Project Location
There are various navigable waterway systems that are included in this project.Latest Updates
Work began on March 10, 2026. Debris removal has been completed as of June 18, 2026. The contractor removed approximately 2319 cubic yards of debris from the waterways. Project is complete and now working on closing out project with NFWF and NOAA.Budget
| Phase | Cost |
|---|---|
| Construction | $800,000 |
| Other Costs | $200,000 |
| Total Budget | $1,000,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 03/10/2026 | 06/19/2026 | 06/18/2026 |
| Turnover & Closeout | 06/19/2026 | 08/01/2026 |
Supporting Materials
Project Phase
Turnover & Closeout
Last Updated
07/31/2026
Project Number
2026-072
Sponsor Department
Public Works Engineering
Construction Contractor
Looks Great Services of MS, Inc.