Project Description
Hurricane Ian damaged this bridge, we have to modify our existing design contract to include storm-related repairs.
The Midway Bridge over North Spring Lake (#014073) requires engineering services to provide minor rehabilitation and maintenance to the bridge structure.
Project Location
The bridge is located on Midway Boulevard just southwest of US 41 over North Spring Lake.Latest Updates
Upcoming Project Activities - March 2023
Hurricane Ian has damaged this bridge and we are modifying the current design contract to include storm-related repairs. We are currently meeting with FDOT and other agencies to get this process started.
The design firm is finalizing the 100% construction plans and the technical specifications.
We are still pending our Army Corps of Engineers (ACOE) permit.
Budget
Phase | Cost |
---|---|
Design | $88,735.05 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 10/07/2021 | 09/09/2022 | |
Construction | 11/14/2022 | 05/16/2023 |
Project Phase
Design Development
Last Updated
03/17/2023
Project Manager
Kelly Slaughter
Public Relations
Tracy Doherty
Email Public Relations
Project Number
2021002053
Sponsor Department
Public Works
Design Engineer/Architect
HDR
Construction Contractor
TBD