Project Description
Replacement of Cedar Point Environmental Park pier with enhanced design for seagrass wading tours.Project Location
Cedar Point Environmental Park
2300 Placida Road, Englewood, FL 34224
Latest Updates
Design and Permitting complete. Finalizing bid documents for procurement. Proceeding to construction bid.Budget
| Phase | Cost |
|---|---|
| Design | $35,000 |
| Construction | $200,000.00 |
| Total Budget | $235,000.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 11/30/2024 | 03/15/2026 | 07/07/2026 |
Project Phase
Design Development
Last Updated
08/06/2026
Sponsor Department
Community Services
Design Engineer/Architect
Coastal Engineering Consultants, Inc.