Rotonda Bridge Rehabilitations Design #3 - Bridges 014098 and 014099

Project Description

Rotonda West MSBU has 17 bridges needing design services to implement the FDOT maintenance and repair items for each of the respective bridges.

This project is for design services for bridge rehabiliations - Bridges #014098 and #014099

Rotonda Circle over Pebble Creek - Bridge #014098

Rebel Court over Rotonda River - Bridge #014099

Project Location

Rotonda Circle over Pebble Creek - Bridge #014098

Rebel Court over Rotonda River - Bridge #014099

See Location Map below.

Latest Updates

Upcoming Project Activities  March 2024

Construction bids were opened and Villa Fuerte Construction was the lowest bidder with an approved contract from the Board of County Commissioners.  

Bridge #014098 (Rotonda Circle over Pebble Creek) will be completed and the lane closure open to traffic on March 22, 2024.

Construction will begin on March 26, 2024, with bridge #014099 (Rebel Court over Rotonda River), this bridge should be completed on May 5, 2024. This bridge will have a temporary lane closure until the bridge construction is complete.

Please exercise caution when traveling in the vicinity of construction zones. 

Budget

Phase Cost
Design $134,770
Construction $709,281.30
Funding source(s): Rotonda West MSBU

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 05/25/2022 06/30/2022
Design Development 06/07/2022 06/24/2023
Construction 02/20/2024 05/05/2024

Supporting Materials

Project Phase
Construction

Last Updated
03/19/2024

Project Manager
Kelly Slaughter

Public Relations
Tracy Doherty
Email Public Relations

Project Number
2022000429

Sponsor Department
Public Works

Design Engineer/Architect
Bridging Solutions/KCI

Construction Contractor
Villa Fuerte Construction