Project Description
Design and construct a 6' sidewalk on the East side of Atwater St. from Veterans Boulevard to Hillsborough Boulevard as part of the 2020 Sales Tax Initiative to connect multiple sidewalk to make community more walkable.Project Location
Veterans Blvd. to Hillsborough Blvd.Latest Updates
The 100% plans have been received and are under review by staff.
The SWFWMD permit has been issued.
Budget
| Phase | Cost |
|---|---|
| Design | $87,555.00 |
| Construction | $398,350.00 |
| Total Budget | $485,905.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 04/15/2024 | 07/15/2026 | |
| Construction | 07/18/2026 | 12/04/2026 |
Project Phase
Design Development
Last Updated
08/03/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Kimley-Horn
Construction Contractor
TBD