Project Description
The purpose of this project is to maintain the roadway system of Charlotte County in the following Districts:
- Greater Port Charlotte
- Pirate Harbor
- Woodland Estates
- Road and Bridge
For more information about the roads to be paved within each district, please see Project Maps under Supporting Materials below.
Latest Updates
The Contract has been completed.
Budget
| Phase | Cost |
|---|---|
| Construction | $13,820,475.75 |
| Total Budget | $13,820,475.75 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 07/10/2023 |
Supporting Materials
Project Phase
Completed 01/28/2026
Project Manager
James Layport
Public Relations
Chad Ray
Email Public Relations
Project Number
2023000348
Sponsor Department
Public Works
Construction Contractor
Ajax Paving, Inc.