Project Description
The purpose of this project is to maintain the roadway system of Charlotte County in the following Districts:
- Greater Port Charlotte
- Lemon Bay
- South Burnt Store
For more information about the roads to be paved within each district, please see Project Maps under Supporting Materials below.
Project Location
- Greater Port Charlotte
- Lemon Bay
- South Burnt Store
Latest Updates
This Contract is substantially complete, with a change order to be completed on the Cape Horn Blvd turn-out onto Burnt Store Road.
Budget
| Phase | Cost |
|---|---|
| Construction | $20,284,893.75 |
| Total Budget | $20,284,893.75 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 08/19/2024 |
Supporting Materials
Project Phase
Construction
Last Updated
11/18/2025
Project Manager
James Layport
Public Relations
Chad Ray
Email Public Relations
Project Number
2024000247
Sponsor Department
Public Works Engineering
Construction Contractor
Preferred Material, Inc.