Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Ackerman Wastewater Expansion

Project Description

The Ackerman MSBU was approved in November 2019. This project includes construction of a wastewater collection system to service approximately 1,300 properties with sewer service, new water service lines and a vacuum station that will provide sewer collection for the wastewater system. 

Project Updates
  • Discussion of an increase in assessment rates for the residents due to increased construction costs has occurred. Once a final rate has been decided, a public hearing will be set and residents will be notified. 
  • Zone 1 — Connections Complete
  • The BCC approved the contract for Zones 3, 4, and LPS. Contractor: Forsberg Construction, Inc. 
    • Zone 3 — Construction began in March 2025. 
  • Due to unexpected circumstances beyond our control involving the contractor, there will be a delay for customers scheduled for Zone 2 connections. We understand the inconvenience this may cause and remain fully committed to progressing the project as quickly as possible. We will continue to share updates as new information becomes available.
    • Total Connections as of May: 430.
  • Installation Agreements for zones 1, 2 and 3 have been mailed out. Please sign and return them to the Utilities Department as soon as possible.
  • Construction of the water line replacement and sewer main installation in zones 1 and 2 is complete. The vacuum station is currently operational. Water line replacement for zone 3 has begun.

Capital Projects Office
Phone: 941.764.4305
Email: S2S@CharlotteCountyFL.gov

Project Location

Throughout the Ackerman Avenue neighborhood. 

The vacuum station located at, 18330 Ackerman Avenue is currently operational.

Project Impacts

Residents in the Ackerman project area may experience low water pressure for the next few months. Crews are currently transferring over to the water new lines and flushing to keep chlorine residuals up in the area. Work also includes connecting customers to the newly installed lines. 

Crews are encountering large amounts of rock during excavation, which has resulted in an unplanned rock crushing operation at the construction yard. 

Latest Updates

Budget

Phase Cost
Total Budget $51,693,929.23
Funding source(s):

Resident Assessments, Florida Department of Environmental Protection State Revolving Funds, EPA Grants, RESTORE, Utility Repair and Replacement Funds.

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 11/19/2019 12/01/2020 12/01/2020
Design Development 01/21/2021 02/01/2022 02/01/2022
Construction 04/05/2021 10/03/2028

Supporting Materials

Project Phase
Construction

Last Updated
06/25/2025

Project Manager
Jody Pressley

Public Relations
Stuart Gooden
Email Public Relations

Sponsor Department
Utilities

Design Engineer/Architect
Giffels-Webster Engineers

Construction Contractor
Forsberg Construction, Inc

Delivering Exceptional Service

Questions? Issues?

Contact Us