Project Description

The Ainger Creek Bridge on CR775, originally constructed in 1981, required emergency repairs due to spalled concrete beneath the bridge deck.

This project involves procuring an engineering firm to design the necessary repairs, followed by contracting with a construction firm to perform the repair work.

Project Location

Ainger Creek Bridge on CR775

Latest Updates

Project Activity - July 2026

The Ainger Creek Bridge required an emergency repair, prompting the County to close a channel beneath the bridge and one vehicular lane until the project is completed.

The contractor is scheduled to begin construction on August 17, 2026.

Budget

Phase Cost
Design $18,875
Construction $257,643.23
Funding source(s): Road and Bridge (Gas Tax)

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 04/02/2026 05/15/2026
Construction 08/17/2026 12/15/2026

Project Phase
Construction

Last Updated
07/16/2026

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works Engineering

Design Engineer/Architect
Centro Consulting Group

Construction Contractor
Thomas Marine Construction