Project Description
The Ainger Creek Bridge on CR775, originally constructed in 1981, required emergency repairs due to spalled concrete beneath the bridge deck.
This project involves procuring an engineering firm to design the necessary repairs, followed by contracting with a construction firm to perform the repair work.
Project Location
Ainger Creek Bridge on CR775Latest Updates
Project Activity - July 2026
The Ainger Creek Bridge required an emergency repair, prompting the County to close a channel beneath the bridge and one vehicular lane until the project is completed.
The contractor is scheduled to begin construction on August 17, 2026.
Budget
| Phase | Cost |
|---|---|
| Design | $18,875 |
| Construction | $257,643.23 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 04/02/2026 | 05/15/2026 | |
| Construction | 08/17/2026 | 12/15/2026 |
Project Phase
Construction
Last Updated
07/16/2026
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Centro Consulting Group
Construction Contractor
Thomas Marine Construction