Project Description
The final hurricane Irma related facilities project was to repair and stabilize the existing canoe/kayak launch along with installing a living shoreline at Allapatchee shores park. Completed 22 days ahead of schedule, the project not only remedied damages caused by Hurricane Irma, but also included repairs to the storm water management system, road, and associated infrastructure.
Project Location
3100 Hickory Court, Punta GordaBudget
Phase | Cost |
---|---|
Design | $63,000.00 |
Construction | $300,000.00 |
Total Budget | $363,000.000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 06/18/2020 | 11/17/2020 | 10/26/2020 |
Turnover & Closeout | 11/09/2020 | 11/17/2020 | 10/26/2020 |
Project Phase
Project Complete
Last Updated
02/22/2021
Project Manager
Justin Dunn
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Community Services
Design Engineer/Architect
Stantec Consulting Services, Inc
Construction Contractor
V & H Construction