Charlotte County, FL Logo

941.743.1200
18500 Murdock Circle
Port Charlotte, FL 33948

Mobile Menu close icon
close search

Alligator Creek Maintenance Dredge

Project Description

The objective of the project is to construct a maintenance dredge event along portions of the Alligator Creek access channel and main channel of the north branch. We must enter a design phase with an engineering firm first, to design, permit and included bid process assistance and construction oversight of the dredge event. This work has been requested by the MSBU Waterway Advisory Board and will be fund by the same. Since the last dredge event in 2017 and a small spot dredge of access channel in 2019, new concern has been brought to the Advisory Board and the county prompting the initiation of this contract. The channel was last surveyed in 2021 and those bathymetric results were reviewed with the AB. Those results and current allowable budget were the basis for the locations that are proposed for the future dredge event. This project is targeting shoaled in sediment above -6' @ Mean Low Water from the access channel inland north of the marina approximately 9300' of project limits and targeting roughly 3400 cubic yards of material. This project will restore depth and width of the navigated channel.

Project Location

Alligator Creek, Punta Gorda Fl

Project Impacts

Improved and safer navigation

Latest Updates

After long delays experienced in negotiating design scope and fees and delays from Covid, Staffing, and hurricane Ian, county management has entered a design contract with Coastal Engineering Consultants. CEC coordinating with project management has completed their desk top review of the project and had recently sent permit applications to FDEP and USACE. There has been reports from citizen that shoaling within the access channel may have got worse because of hurricane Ian. County management has entered a purchase request to hire a firm to perform a post- storm bathymetric survey and to provide technical support in obtaining FEMA aid if damages are confirmed. This survey will be used as well to update project documents. As of Mid-March, the county has selected a firm for the post-storm bathymetric survey's, which include Alligator creek. The county and consultant are currently in negotiations of scope and fee. It is anticipated that the survey will be conducted, and deliverables received by early summer. We still await responses from permitting agencies pertaining to the current dredge design project. 

Budget

Phase Cost
Engineering $76,990.00
Construction $300,000.00
Total Budget $376,990.00
Funding source(s): Alligator Creek Waterway MSBU

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Planning and Approval 01/20/2022 04/20/2022
Design Development 04/20/2022 02/12/2024
Construction 05/01/2024 08/01/2024
Turnover & Closeout 08/02/2024 08/16/2024
Alligator Creek Maintenance Dredge Project Image

Project Phase
Design Development

Last Updated
03/23/2023

Project Manager
Zach Patchell

Public Relations
Karlene McDonald
Email Public Relations

Project Number
c392003

Sponsor Department
Public Works

Design Engineer/Architect
Atkins

Construction Contractor
TBD

Delivering Exceptional Service

Questions? Issues?

Contact Us