Project Description
A Master Developement Order agreement between Charlotte County and the developer has been made to build a new Law Enforcement Office located in southern Charlotte County as part of the Master Babcock Ranch Concept Plan.Project Location
17755 Curry Preserve Drive, Punta GordaProject Impacts
No expected delays or impacts to the project.Latest Updates
On May 6th, community leaders, first responders, and residents gathered for the official ribbon cutting ceremony celebrating the opening of the new Charlotte County Fire Station 9 and Charlotte County Sheriff’s Office District 5 facilities. This event marked a significant milestone in enhancing public safety infrastructure in Babcock Ranch by displaying the product of a collaboration on a project between Charlotte County and Kitson of Partners. The opening of these facilities brings enhanced emergency services directly into the heart of Babcock Ranch, ensuring faster response times and a strengthened sense of security for residents. As the population grows, these services are critical for supporting long-term community health, safety, and quality of life.
Budget
Phase | Cost |
---|---|
Design | $500,000 |
Engineering | $658,741 |
Construction | $2730810 |
Total Budget | $3,677,770 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 01/01/2023 | 08/01/2023 | 08/01/2023 |
Design Development | 01/01/2023 | 08/01/2023 | 08/01/2023 |
Construction | 12/01/2023 | 01/01/2025 | 01/10/2025 |
Turnover & Closeout | 01/01/2025 | 02/11/2025 | 05/06/2025 |
Project Phase
Project Complete
Last Updated
07/17/2025
Public Relations
Brian Gleason
Email Public Relations
Project Number
c892201
Sponsor Department
CCSO Sheriff's Dept
Design Engineer/Architect
Fawley Bryant Architecture
Construction Contractor
Florida Premier Contractors