Project Description
Demolition and complete replacement/repair of the vertical seawall, safety railing, erosion and upland walkway (adjacent to playground area restroom building) at Bayshore Live Oak Park.Project Location
Bayshore Live Oak Park
23157 Bayshore Road, Port Charlotte, FL 33980.
Project Impacts
90% plans complete. USACE permit received. Waiting on final FDEP and SWFWMD approval. Bid docs expected with completed approvals 11/25.Budget
Phase | Cost |
---|---|
Design | $116,000.00 |
Construction | $867,184.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 02/01/2025 | 11/01/2025 |
Project Phase
Planning and Project Approval
Last Updated
09/30/2025
Project Manager
Lonne Moore
Public Relations
Breanna Benevenga
Email Public Relations
Sponsor Department
Community Services
Design Engineer/Architect
Weiler Engineering Corp.