Project Description
Bermont Road Box Culvert Rehabilitations - This project has four box culverts needing design services to implement the FDOT maintenance and repair items for each of the respective box culverts.
CR 74 (Bermont Road) over Myrtle Slough - #010003
CR 74 (Bermont Road) over Shell Creek Drainage - #010016
CR 74 (Bermont Road) over Babcock Drainage - #010017
CR 74 (Bermont Road) over Myrtle Slough - #010020
Project Location
CR 74 (Bermont Road) over Myrtle Slough - #010003
CR 74 (Bermont Road) over Shell Creek Drainage - #010016
CR 74 (Bermont Road) over Babcock Drainage - #010017
CR 74 (Bermont Road) over Myrtle Slough - #010020
Latest Updates
Upcoming Project Activities for November 2024
The County approved the Bridge Repair Memorandum on September 20, 2024. We expect the 100% plans and construction documents by November 15, 2024.
Budget
Phase | Cost |
---|---|
Design | $139,890 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 04/15/2024 | 10/11/2024 |
Project Phase
Design Development
Last Updated
10/31/2024
Project Manager
Kelly Slaughter
Public Relations
Brian Gleason
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Weiler Engineering Corp