Project Description
Bermont Road Box Culvert Rehabilitations - This project has four box culverts needing design services to implement the FDOT maintenance and repair items for each of the respective box culverts.
CR 74 (Bermont Road) over Myrtle Slough - #010003
CR 74 (Bermont Road) over Shell Creek Drainage - #010016
CR 74 (Bermont Road) over Babcock Drainage - #010017
CR 74 (Bermont Road) over Myrtle Slough - #010020
Project Location
CR 74 (Bermont Road) over Myrtle Slough - #010003
CR 74 (Bermont Road) over Shell Creek Drainage - #010016
CR 74 (Bermont Road) over Babcock Drainage - #010017
CR 74 (Bermont Road) over Myrtle Slough - #010020
Latest Updates
Upcoming Project Activities for April 2025
The County has approved all plans and construction documents and is submitting them to the Purchasing Department for bid processing.
Budget
Phase | Cost |
---|---|
Design | $139,890 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 04/15/2024 | 02/28/2025 |
Project Phase
Design Development
Last Updated
04/10/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Weiler Engineering Corp