Project Description
These 2 bridges currently require design services to implement the FDOT maintenance and repair items for each of the respective bridges.
Bridge #010061 is County Road 775 over Buck Creek.
Bridge #010063 is on County Road 775 over Oyster Creek.
Project Location
Bridge #010061 is County Road 775 over Buck Creek.
Bridge #010063 is on County Road 775 over Oyster Creek.
Latest Updates
The Buck Creek and Oyster Creek Bridge Rehabilitation Projects are complete.
Budget
| Phase | Cost |
|---|---|
| Design | $134,865 |
| Construction | $773,117.73 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 12/14/2023 | 11/25/2024 | |
| Construction | 07/14/2025 | 10/27/2025 | 10/22/2025 |
| Turnover & Closeout | 10/23/2025 | 11/24/2025 |
Project Phase
Completed 12/02/2025
Project Manager
Kelly Slaughter
Public Relations
Chad Ray
Email Public Relations
Project Number
25002524
Sponsor Department
Public Works
Design Engineer/Architect
Kimley-Horn Engineers
Construction Contractor
Thomas Marine Construction