Project Description

These 2 bridges currently require design services to implement the FDOT maintenance and repair items for each of the respective bridges.  

Bridge #010061 is County Road 775 over Buck Creek.

Bridge #010063 is on County Road 775 over Oyster Creek.

Project Location

Bridge #010061 is County Road 775 over Buck Creek.

Bridge #010063 is on County Road 775 over Oyster Creek.

Latest Updates

Project Activities for June 2025

Thomas Marine Construction will start construction on July 14, 2025.   

Budget

Phase Cost
Design $134,865
Construction $773,117.73
Funding source(s): Road and Bridge Gas Tax

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 12/14/2023 11/25/2024
Construction 07/14/2025 10/27/2025

Project Phase
Construction

Last Updated
06/12/2025

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works

Design Engineer/Architect
Kimley-Horn Engineers

Construction Contractor
Thomas Marine Construction