Bridge Scour Study and Countermeasures

Project Description

This project involves conducting a scour analysis and providing recommendations for appropriate scour countermeasures.

Project Location

Tom Adams Bridge over Lemon Bay (#010029)

Ainger Creek Bridge (CR 775) (#010062)

Midway Bridge over N. Spring Lake (#014073)

Latest Updates

Project Update - October 2025

The project kick-off meeting is scheduled for October 9, 2025.  

Budget

Phase Cost
Design $388,108.65
Funding source(s): Road and Bridge

Schedule

Phase Estimated Start Date Forecast Completion Actual Completion
Design Development 10/09/2025

Project Phase
Design Development

Last Updated
10/30/2025

Project Manager
Kelly Slaughter

Public Relations
Chad Ray
Email Public Relations

Sponsor Department
Public Works Engineering

Design Engineer/Architect
DRMP Engineering