Project Description
Renovate Charlotte County Administration Center, Murdock Campus, Building D to accommodate the growing needs of the Facilities Construction and Maintenance Department.
Project Location
18500 Murdock Circle, Building-D, Port Charlotte, Florida 33948.Project Impacts
Weather
Florida Department of Environmental Protection
South West Florida Water Management District
Latest Updates
Community Development has completed their review signed and sealed are good to go. Building-D project has been transfered over to small projects for construction.
Budget
| Phase | Cost | 
|---|---|
| Design | $80,000 | 
| Construction | $800,000 | 
| Total Budget | $880,000.00 | 
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion | 
|---|---|---|---|
| Planning and Approval | 06/08/2023 | 01/30/2024 | 02/29/2024 | 
| Design Development | 04/02/2024 | 10/01/2024 | 12/30/2024 | 
| Construction | 10/23/2024 | 05/27/2026 | |
| Turnover & Closeout | 05/29/2026 | 06/25/2026 | 
          Project Phase
           
           
          
          Construction
           
           
           
        
          Last Updated
          10/20/2025
        
          Project Manager
          Pedro Agosto
        
          Public Relations
          Brian Gleason
          Email Public Relations
        
          Project Number
          c192201
        
          Sponsor Department
          Facilities
        
          Design Engineer/Architect
          Fawley Bryant
        
          Construction Contractor
          TBD
        