Project Description
Renovate Charlotte County Administration Center, Murdock Campus, Building D to accommodate the growing needs of the Facilities Construction and Maintenance Department.
Project Location
18500 Murdock Circle, Building-D, Port Charlotte, Florida 33948.Project Impacts
Weather
Florida Department of Environmental Protection
South West Florida Water Management District
Latest Updates
Design Team: Fawley Bryant Signed and sealed plans have been submitted to the Building Department to work on county permitting requirements. Community Development has completed their review signed and sealed are good to go. Building-D project has been handed over to small projects for construction.
Budget
Phase | Cost |
---|---|
Design | $80,000 |
Construction | $800,000 |
Total Budget | $880,000 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 06/08/2023 | 01/30/2024 | |
Design Development | 04/02/2024 | 10/01/2024 | 12/30/2024 |
Construction | 10/23/2024 | 10/23/2025 | |
Turnover & Closeout | 10/31/2025 | 12/01/2025 |
Project Phase
Construction
Last Updated
04/23/2025
Project Manager
Pedro Agosto
Public Relations
Brian Gleason
Email Public Relations
Project Number
c192201
Sponsor Department
Facilities
Design Engineer/Architect
Fawley Bryant
Construction Contractor
TBD