Project Description
The project will add two sidewalks, one on Caring Way, from Olean Boulevard to Gertrude Avenue, and one on Brinson Avenue, from Caring Way to Harbor Boulevard. Additionally, the project will incorporate the removal and replacement of any of Charlotte County Utility Department's (CCUD) infrastructure located under or impacted by the future sidewalks.
The project may be constructed as one or two separate projects, which will be determined before the bid advertisement.
Project Location
Caring Way, from Olean Boulevard to Gertrude Avenue
Brinson Avenue, from Caring Way to Harbor Boulevard
Latest Updates
The 30% design plans have been reviewed, with comments provided to the Engineer of Record (EOR) for revision. The 60% plans are scheduled for submission in October.
Budget
| Phase | Cost |
|---|---|
| Design | $181,080.00 |
| Construction | $700,000 |
| Total Budget | $881,080.00 |
Sidewalk portion will be funded through sales tax
CCUD portion will be funded by the utility
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 09/08/2022 | 09/30/2023 | 10/31/2023 |
| Design Development | 08/12/2024 | 11/03/2025 | |
| Construction | 12/01/2025 | 07/31/2025 | |
| Turnover & Closeout | 08/04/2025 | 09/30/2025 |
Project Phase
Design Development
Last Updated
10/29/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Project Number
2023000366
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD