Project Description
Replacement of Cedar Point Environmental Park pier with enhanced design for seagrass wading tours.Project Location
Cedar Point Environmental Park
2300 Placida Road, Englewood, FL 34224
Project Impacts
This project timeline was reset due to Hurricane Milton completely destroying the pier. USACE permit approved. Plans revised due to FDEP RAI (seagrass) waiting on response.Budget
Phase | Cost |
---|---|
Design | $35,000 |
Construction | $200,000.00 |
Total Budget | $235,000.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 11/30/2024 | 11/01/2025 |
Project Phase
Planning and Project Approval
Last Updated
09/30/2025
Project Manager
Lonne Moore