Project Description
The NWPC Street & Drainage MSBU has requested a sidewalk be designed & constructed on Chamberlain Blvd. from US-41 to Campbell St. for improved walkability. The project was devided into two phases. Phase 1 is from US-41 to Jacobs St. Phase 2 is Jacobs St. to Campbell St.Project Location
The project runs along the north side of Chamberlain Blvd. Phase 1 is from US-41 to Jacobs Street. Phase 2 is from Jacobs Street to Campbell Street.Latest Updates
The consultant is preparing the 90% design plans, which are due in mid-January. They are also coordinating with SWFWMD regarding the permit exemptionBudget
| Phase | Cost |
|---|---|
| Design | $264,983.00 |
| Construction | $2,360,000.00 |
| Total Budget | $2,624,983.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Design Development | 09/09/2024 | 05/01/2026 | |
| Construction | 08/03/2026 | 02/01/2027 |
Project Phase
Design Development
Last Updated
01/13/2026
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works Engineering


