Project Description
This project includes the design and construction of a new pedestrian sidewalk on Melbourne Street from US 41 to Harborview Road.Project Location
Melbourne Street from US 41 to Harborview Road in Charlotte Harbor.Latest Updates
Johnson Engineering is currently coordinating with private utility stakeholders to resolve conflicts, which will be incorporated into the final construction plans.
Real Estate Services is in the process of acquiring Temporary Rights of Entry from various property owners along the project corridor.
Additionally, Johnson Engineering is preparing a Change Order to include additional sidewalk improvements from the Dick Loftis Bridge to US 41. Upon approval of this Change Order, the construction plans will be updated accordingly.
Budget
| Phase | Cost |
|---|---|
| Design | $288,080 |
| Construction | $2,730,000 |
| Total Budget | $3,018,080.00 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Planning and Approval | 01/10/2022 | 07/11/2022 | 07/08/2022 |
| Design Development | 07/12/2022 | 12/19/2025 | |
| Construction | 04/27/2026 | 12/25/2026 |
Supporting Materials
Project Phase
Design Development
Last Updated
01/15/2026
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
c192205
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD