Project Description
This project includes the design and construction of Parmely Street from U.S. 41 to Bayshore Road. This design is to widen the existing roadway to twenty-four feet wide and includes a pedestrian sidewalk from U.S. 41 to Bayshore Road.Project Location
Parmely Street from US 41 to Bayshore Road in Charlotte HarborProject Impacts
Due to Hurricane Ian, the scheduled has been delayed.Latest Updates
Johnson Engineering has started the initial survey and is currently working on the 30 percent design phase. 30% design plans are due on March 6, 2023
Budget
Phase | Cost |
---|---|
Design | $149,700 |
Construction | $500,000 |
Total Budget | $649,700 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 01/10/2022 | 07/11/2022 | 07/08/2022 |
Design Development | 07/11/2022 | 01/08/2024 | |
Construction | 04/01/2024 | 09/30/2024 | |
Turnover & Closeout | 10/01/2024 | 10/31/2024 |

Project Phase
Design Development
Last Updated
01/23/2023
Project Manager
Jeff Keyser
Public Relations
Tracy Doherty
Email Public Relations
Project Number
c192207
Sponsor Department
Public Works
Design Engineer/Architect
Johnson Engineering
Construction Contractor
TBD