Project Description
This project incorporates the design and construction of new turn lanes and traffic signal modifications. New left and right turn lanes will be added to Cochran and Veterans Boulevard intersection along with roadway widening, drainage improvments, signal modifications, sidewalks, and pedestrian crosswalk improvements.
Project Location
Cochran Boulevard from Peachland Boulevard to Kenllworth BoulevardProject Impacts
The bid opening has been delayed due to the recent Hurricanes.Latest Updates
Veterans Boulevard @ Cochran Boulevard intersection project is currently out for bid. Bid opening is scheduled for November 2024.
Budget
Phase | Cost |
---|---|
Design | $340,277 |
Construction | $3,341,566.53 |
Total Budget | $3,681,843.53 |
Gas Tax C411620
State Funded Grant
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/11/2019 | 08/04/2019 | 08/14/2019 |
Design Development | 09/02/2020 | 06/24/2024 | 06/21/2024 |
Construction | 12/16/2024 | 06/20/2025 |
Supporting Materials
Project Phase
Design Development
Last Updated
10/14/2024
Project Manager
Jeff Keyser
Public Relations
Tracy Doherty
Email Public Relations
Project Number
19-279
Sponsor Department
Public Works
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
TBD