Project Description
This project incorporates the design and construction of new turn lanes and traffic signal modifications. New left and right turn lanes will be added to Cochran and Veterans Boulevard intersection along with roadway widening, drainage improvments, signal modifications, sidewalks, and pedestrian crosswalk improvements.
Project Location
Cochran Boulevard from Peachland Boulevard to Kenllworth BoulevardLatest Updates
EHC Inc. has submited all their Bond paperwork for the project.
Lighted message boards will be on site two weeks prior to the start of construction notifying the motoring public for the upcoming work.
Construction is scheduled to start on May 19, 2025
Budget
Phase | Cost |
---|---|
Design | $340,277 |
Construction | $3,341,566.53 |
Total Budget | $3,681,843.53 |
Gas Tax C411620
State Funded Grant
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Planning and Approval | 02/11/2019 | 08/04/2019 | 08/14/2019 |
Design Development | 09/02/2020 | 06/24/2024 | 06/21/2024 |
Construction | 05/19/2025 | 11/15/2025 |
Supporting Materials

Project Phase
Construction
Last Updated
02/03/2025
Project Manager
Jeff Keyser
Public Relations
Chad Ray
Email Public Relations
Project Number
19-279
Sponsor Department
Public Works
Design Engineer/Architect
Florida Transportation Engineering
Construction Contractor
TBD