Project Description
Construction of reclaimed water mains along the right-of-way of Cochran Boulevard from Quesada Avenue to Peachland Boulevard.Project Location
Cochran Boulevard from Quesada Avenue to Peachland Boulevard.Project Impacts
Crews are working along Quesada Avenue.
Latest Updates
The contractor is temporarily storing project materials at the Quesada Avenue Lift Station.
Work has resumed on this project as of December 2024. Crews are working along Quesada Avenue.
The sidewalk along Peachland Boulevard, from Heritage Oak Park to Cochran Boulevard, will be closed starting Thursday, April 3, through Thursday, April 10.
Budget
Phase | Cost |
---|---|
Construction | $757,902.08 |
Total Budget | $757,902.08 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 11/18/2022 | 05/27/2025 |
Project Phase
Construction
Last Updated
04/21/2025
Project Manager
Hendrik Dolleman
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Construction Contractor
Accurate Drilling Systems