Project Description
Construction of reclaimed water mains along the right-of-way of Cochran Boulevard from Quesada Avenue to Peachland Boulevard. The project will install of approximately 3,010 linear feet of 6-inch and 2,850 linear feet of 8-inch reclaimed water distribution main, connection to the existing main, installation of service lines, change-over from potable water to reclaimed water on existing irrigation lines and plugging of abandoned potable water service taps.Project Location
Cochran Boulevard from Quesada Avenue to Peachland Boulevard.Project Impacts
The contractor is waiting on licensing requirements due to a name change. Construction can not start until the licensing is complete.
Design updates are needed along the project. This has extended the project completion timeframe.
Latest Updates
The contractor is temporarily storing project materials at the Quesada Avenue Lift Station.Budget
Phase | Cost |
---|---|
Construction | $1,345,650.76 |
Total Budget | $1,345,650.76 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Construction | 11/18/2022 | 09/30/2023 |
Project Phase
Construction
Last Updated
08/25/2023
Project Manager
Hendrik Dolleman
Public Relations
Caroline Wannall
Email Public Relations
Sponsor Department
Utilities
Construction Contractor
Shipps Excavating Inc.