Project Description
The county shall construct landscape and irrigation improvements in the median and right of way of CR 771 (Gasparilla Road) between SR 776 and Marathon Boulevard.Project Location
CR 771 (Gasparilla Road) between SR 776 and Marathon Boulevard in both the median and the right of way.Project Impacts
This project experienced delays due to the signalization of the intersection of CR 771 and Marathon Boulevard, Hurricane Ian, Hurricane Milton, and the resulting impact of restoration work on the budget.Latest Updates
Work on the project is complete other than the engineer of record's punch list of final items. Punch list items are scheduled for completion during the last week of January 2026.Budget
| Phase | Cost |
|---|---|
| Engineering | $60,395.00 |
| Construction | $621,829.98 |
| Total Budget | $682,224.98 |
Schedule
| Phase | Estimated Start Date | Forecast Completion | Actual Completion |
|---|---|---|---|
| Construction | 05/19/2025 | 06/23/2025 | |
| Turnover & Closeout | 06/16/2026 | 07/01/2026 |
Supporting Materials
Project Phase
Construction
Last Updated
03/02/2026
Project Manager
Chuck Peters
Public Relations
Chad Ray
Email Public Relations
Project Number
23-335
Sponsor Department
Public Works Engineering
Design Engineer/Architect
Johnson Engineering
Construction Contractor
BrightView Landscape Services, Inc