Project Description
This project will consist of replacing all light poles felled by Hurricane Ian.
Several streetlights remain out due to repeated wire theft. Although repairs have been completed, theft has occurred again at some locations, resulting in continued outages.
As of June 6, 2026 all wire has been replaced. We have started the LED conversion of Burnt Store Rd, starting at U.S. 41 heading south.
Public Relations: Chad Ray
Project Managers:
- Jody Mansell
Project Location
Burnt Store Rd from US 41 to County Line.
The Federal Highway Administration (FHWA) process is the final approval needed before a federally funded transportation project can move forward. FHWA reviews the project to confirm it meets federal requirements and is eligible for reimbursement. Once authorization is issued, the project can proceed and costs become eligible for federal funding. Until then, work is limited to avoid jeopardizing reimbursement.
Project Impacts
Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event |
|---|---|---|---|
|
Work Type |
TBD |
TBD |
Ian |
|
Work Type |
TBD |
TBD |
Ian |
|
Work Type |
TBD |
TBD |
Ian |
|
Work Type |
TBD |
TBD |
Ian |
|
Work Type |
TBD |
TBD |
Ian |
Budget
| Phase | Cost |
|---|---|
| Total Budget | $37,844.25 |
Last Updated
08/03/2026