Project Description
Storm damage impacted playground and restroom facilities at the site. Playground equipment suffered damage to 1,950 sq. ft. of shade structure. Restroom components were damaged, including two reinforced concrete slabs, two extended offset single post pyramid structures with 9-ft. eaves, columns with powder-coated finishes, weld flanges, and eight hip rail beams. Additionally, two basketball hoops/nets need to be replaced, and one park rules sign requires resetting onsite.
Public Relations:
Project Managers:
- Lonne Moore
Project Location
25555 Sandhill Blvd., Deep Creek, FL 33983Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event |
|---|---|---|---|
|
Buildings |
Ian | ||
|
Signage |
Ian | ||
|
Park amenities |
11/10/2025 | 2/10/2026 | Ian |
Budget
| Phase | Cost |
|---|---|
| Total Budget | $272,600.00 |