Project Description
Multiple facility damages were reported, including fencing losses across tennis courts, baseball fields, playgrounds, and the maintenance yard; numerous missing split rail post caps; and several signage replacements. Buildings sustained various roof, siding, soffit, fascia, and gutter damages, with some carports and sheds being total losses. Recreational structures affected include pickleball nets, playground shades, bleacher sections, dugout canopies, batting tunnels, and sports field lighting. Additional issues include damaged flagpoles, lighting fixtures, parking lot lights, and erosion-related impacts. Mitigation efforts to date included water extraction, drying, and temporary roof measures.
Public Relations:
- Breanna Benevenga
 
Project Managers:
- Lonne Moore
 - Joseph Romanelli
 
Project Location
23400 Harold Ave., Port Charlotte, FL 33952Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event | 
|---|---|---|---|
| 
			 Recovery site  | 
			Ian | ||
| 
			 Buildings  | 
			Ian, Helene, Milton | ||
| 
			 Fencing  | 
			Ian | ||
| 
			 Lighting  | 
			Ian | ||
| 
			 Signage  | 
			Ian | ||
| 
			 Park amenities  | 
			11/10/2025 | 2/10/2026 | Ian, Helene | 
Budget
| Phase | Cost | 
|---|---|
| Total Budget | $79,959.56 | 



                          
                          
                          
                          
      
                        
      
      
      