Project Description
Two gazebos sustained extensive structural damage, including broken wood posts, top rails, cross flats, center rails, bench boards, bracing, lattice panels, roof support beams, and metal brackets, along with damaged bolts and fasteners. Various site signage was also damaged or missing. In addition, a 15-foot section of steel vehicle guardrail was damaged, including the end cap, two wood posts with blocks, and associated carriage bolts.
Public Relations:
Project Managers:
- Lonne Moore
Project Location
9000 St. Paul Drive, Port Charlotte FL 33981Latest Updates
| Description of Work | Estimated Start | Estimated Completion | Storm Event | 
|---|---|---|---|
| Signage | Ian | ||
| Pavilions | 10/15/2025 | 3/16/2025 | Ian | 
Budget
| Phase | Cost | 
|---|---|
| Total Budget | $28,733.00 | 



 
                           
                           
                           
                           
      
                        
      
      
      