Project Description
The Greater Port Charlotte Street & Drainage MSBU advisory board has requested the design and construction of a new 6' sidewalk on Dorchester, Bachmann Boulevard and Yancy Street.Project Location
This project will include the design of new 6-foot sidewalks on the Southside of Bachmann Boulevard from Atwater Street to Dorchester Street, on the West side of Dorchester Street from Bachmann Boulevard to Yancy Street, and the West side of Yancy Street from Dorchester Street to Midway Boulevard.Latest Updates
The MSBU committee vote to split this project into 2 phases for construction phase 1 will be from Midway Blvd. to Peachland Blvd. phase 2 will be from Peachland Blvd. to Atwater St. The project pre-construction meeting was held and Feb. 3rd. 2025 was set as the start date. FPL crews are on site trimming vegetation to allow for the relocation of their poles as they complete this the contractor will set up to start their work. The watermain replacement will take place first with the sidewalk following behind that.Budget
Phase | Cost |
---|---|
Design | $155,255.00 |
Construction | $1,700,000.00 |
Total Budget | $1,855,255.00 |
Schedule
Phase | Estimated Start Date | Forecast Completion | Actual Completion |
---|---|---|---|
Design Development | 07/07/2020 | 02/25/2022 | 03/01/2022 |
Construction | 02/03/2025 | 03/10/2026 | |
Turnover & Closeout | 04/06/2026 | 04/30/2026 |
Supporting Materials
Project Phase
Construction
Last Updated
03/12/2025
Project Manager
Raymond Slade
Public Relations
Chad Ray
Email Public Relations
Sponsor Department
Public Works
Design Engineer/Architect
Southwest Engineering & Design, Inc. (SED)
Construction Contractor
TBD